Project Description
Location: UAE
Year Completed: 2008
RCG installed the biggest GIS sub-station in Dubai, where it constructed and commissioned 29 x 132 kV bays and 23 x 400 kV bays for DEWA.
Substation 400/132 kV (Erection and commissioning); including Scada and communication system (24 bay 400kV).