AMANDI 192 MW CCPP

Project Description

Location: Ghana
Year Completed: 2018- ongoing

The scope of work consisted of the mechanical and electrical erection of a combined cycle power plant generating a total of 192MW. The main mechanical parts of the power plant were the HRSG, GTG, STG, and ACC.

RCG did the erection of all the structural works, 5 modules (ranging from 70Ton to 210Ton), casing, HP and LP drums, casing insulation, and cladding, in addition, all HRSG’s piping work adding to 9000-inch diameter from different alloy steels (CS, SS, P91, P22, and P11)

RCG was responsible for the mechanical erection of the GTG along with its auxiliaries, alignment, GT’s piping, and tubing and GTG enclosure

RCG’s main duty was the mechanical erection and alignment of STG and its auxiliaries, piping, tubing and STG main enclosure. RCG’s piping work on the STG was mainly and not limited to the HP/LP, auxiliary, seal steam and lube oil lines

ACC’s mechanical scope consisted on the erection of the steel structure and mechanical components (such as fan bridges, A-frames, fan drives, tube bundles, and cleaning system), preassembly, erection and alignment of exhaust steam duct/steam distribution ducts, piping work and wind wall cladding.

HRSG Rehabilitation at Deir Ammar Power Plant

Project Description

Location: Lebanon
Year Completed:   2018

Dismantling, erecting, installing and maintaining the modules, casing, valves and all related items. Performance of non-destructive controls, hydraulic tests of the HRSG; insulation; final painting

In addition to that, full commissioning, chemical cleaning, steam blowing, HRSG startup, Pumps commissioning was performed.

Talimarjan 900MW CCPP

Project Description

Location: Uzbekistan
Year Completed:   2017

Power plant erection 900 MW; 2 HRSG vertical type; BOP SYSTEMS; related auxiliary systems and piping.

In addition to that, the erection and the pre-commissioning of two power blocks consisting of two HIP/LP Fuji steam turbines 142MW each capacity and two MHI Gas turbines M701F 310 MW capacity each was performed.

Riyadh Power Plant No.10 (PP10)

Project Description

Location: KSA
Year Completed: 2014

Power plant erection 4200 MW (2 of 5 Blocks); 16 HRSG vertical type; BOP SYSTEMS; related auxiliary systems and piping.

WAJBA POWER PLANT

Project Description

Location: Qatar
Year Completed: 2010

Dismantling and shifting of 90 MVA transformer 15/132 kV to SLAYLA Power Plant Erection and Commissioning.

HADJRET EN NOUSS 1200 MW COMBINED CYCLE POWER PLANT (3 UNITS)

Project Description

Location: Algeria
Year Completed:   2009

Auxiliary system installation and pipe rack; mechanical and instrumentation work including steel structure.

Steam blow fabrication and erection, commissioning assistance (mechanical and electrical work)

MARIB 300 MW GAS TURBINE POWER STATION ( 3 UNITS)

Project Description

Location: Yemen
Year Completed: 2007

Power Plan erection, commissioning, operation and maintenance (mechanical, instrumentation and electrical); including Scada and communication system.